The construction of the extension of the "City Concorde" shopping mall is progressing rapidly

With more than 17,000 m³ of excavation, 150 bored piles, 6,700 m³ of concrete, 713,000 kg of reinforcement steel and 84,000 kg of steel structure, the shell of the City Concorde extension building was officially completed on 22 November. Romain and Max Koster organized the “Straußfest” in the presence of many personalities already 14 months after starting work.

The official opening of the extension (12,000 m² gross additional area) is planned for mid-November 2018.