Campus Born from above: A look at the construction progress (LUX)

Current drone footage offers fascinating insights into the construction progress of our "Campus Born" project on the southern edge of the municipality of Rosport-Mompach. From a bird's-eye view, the dimensions of the complex, conceived as a forward-looking place for education, childcare, and community, are revealed. It will house a new school building (cycles 1–4), a Maison Relais, and a multi-purpose hall, complemented by interaction areas, an access road, a bus stop, and around 70 parking spaces.

 

For the school building, the walls of the first upper floor are two-thirds complete, formwork for the slab above is underway; concrete works are scheduled for May. Construction of the second upper floor will follow. The sports hall's exterior walls have already reached their full height, including recesses for the future timber beams. Adjoining areas such as the buvette, changing rooms, and sanitary facilities are taking shape, and roof surfaces are concreted.

 

In the coming weeks, formwork and concreting for the ground floor slab of the sports hall's ancillary structures will follow. The majority of the structural works are expected to be completed before winter. This continuous progress is thanks to the excellent coordination of all involved trades and represents a significant stage on the path to completing "Campus Born".


Drone Shots: © Commune de Rosport-Mompach


Share on