School Campus, Echternach (LUX)

The foundation works for the new school campus of the "Millermoaler Schull" in Echternach have been completed. More than 100 bored piles have been installed, on which the building will later sit. Subsequently, the area of the building’s footprint surrounding the piles has been dug out and replaced with shotcrete. This area will be located under the building and will be accessible for revisions, as well as floodable in case of high water levels. The bored pile heads were sharpened and the reinforcement was put in place. After the Congé Collectif, the pile heads and the reinforcement will be set in concrete to which the foundation slab will then be connected.

 

Photos: ©Fotostudio Creativ